Field in development and production
This section covers projects under development and fields in production. Pre-sanctioned projects, including some discoveries in the early evaluation phase, are also presented.
Exploration activities are described in report section 3.2.3, Operational review-International E&P-Exploration activity. This section often refers to a field's plateau production, which refers to yearly average equity production at plateau for a field 100% (not our share). Capacities also refer to the total field or facility, a 100% share.
The number of development wells as of 31 December 2008 for producing fields is provided under report section 3.2.5 Production above.
The total number of development wells in fields under development that were already drilled or undergoing drilling as of year end 2008 was 127..
| |
| Angola: Gimboa |
20% |
Sonangol |
2006 |
2009 |
| The USA: Tahiti |
25% |
Chevron |
2005 |
2009 |
| The USA: Thunder Hawk |
25% |
Murphy |
2006 |
2009 |
| Brazil: Peregrino |
100% |
StatoilHydro |
2007 |
2011 |
| Canada: Leismer Demonstration Plant (Oil Sands phase 1) |
100% |
StatoilHydro |
2007 |
2010 |
| Ireland: Corrib |
36.50% |
Shell |
2001 |
2010/2011 |
| Angola: Pazflor |
23.33% |
Total |
2007 |
2011 |
| Angola: PSVM |
13.33% |
BP |
2008 |
2012 |