Measures and results 

Safety

 

Planned actions 2008

Results 2008

Planned actions 2009

An indicator linked to technical safety condition will be established.

A status indicator for closing findings from monitoring of technical safety conditions has been implemented.

Improved HSE management training

Develop an HSE culture-building concept for StatoilHydro based on experiences from the safe behaviour programme  (Statoil) and the Gravdal concept (Hydro).

The experiences have been reviewed, and a new compliance programme prepared. Follow-up of the safe behaviour programmes has continued.

A new compliance programme will be implemented.

 

Make active use of the proactive indicator for technical safety condition.

Actively stimulate the remedying of safety-critical faults in technical installations.

The closing of findings is on the scoreboard. Additional information to show other aspects of technical integrity has been defined.

Quarterly new data for technical integrity will be presented to the management. 

Continue the HMS24 initiative at Kårstø. Ongoing. Part of improved HSE training. Simplification and harmonisation of working processes and governing documentation.